pconsult1(m): 2:42pm On May 03, 2024 |
Good day everyone, stay tuned for updates on the construction process of this new project we just started on May 1st, 2024 with setting out and excavation of foundation. It's a combination of 4 bedroom duplex with 2 units of 2 bedroom semi-detached duplex. Project location : Kay Farms Estate, Lagos Project duration: 6 months Do well to us for Architectural design, structural designs, construction and Real estate development/services. "We pleasingly design and build" Call or whatsapp - 07011714010
|
pconsult1(m): 2:51pm On May 03, 2024 |
Excavation..
|
pconsult1(m): 2:52pm On May 03, 2024 |
.
|
pconsult1(m): 12:43pm On May 05, 2024 |
Foundation and column base excavation has been completed
|
Theanchor: 5:25pm On May 05, 2024 |
pconsult1: Width and depth of this your foundation and column bases ![]() |
pconsult1(m): 7:11am On May 06, 2024 |
3D
|
pconsult1(m): 7:16am On May 06, 2024 |
" We pleasingly design and build "
|
pconsult1(m): 7:16am On May 06, 2024 |
us too - 07011714010
|
pconsult1(m): 8:09pm On May 06, 2024 |
Blinding..
|
pconsult1(m): 5:00pm On May 07, 2024 |
Foundation block work underway
|
Hatesin: 9:18pm On May 07, 2024 |
Theanchor: Seems he is just a Labourer at that site. So he can not answer your questions. |
pconsult1(m): 1:32pm On May 08, 2024 |
.
|
pconsult1(m): 1:38pm On May 08, 2024 |
Theanchor:Sorry I'm just seeing this.. 675x800mm 1000 x 300mm respectively |
pconsult1(m): 1:46pm On May 08, 2024 |
Fdn
|
pconsult1(m): 8:49pm On May 08, 2024 |
M
|
pconsult1(m): 8:37pm On May 09, 2024 |
Back filling is ongoing
|
Theanchor: 12:41pm On May 10, 2024 |
pconsult1: Ok. Thanks for your response. But I see some people doing 18" for the width 750mm for the depth and 150mm for the column bases. What can you say about that? |
pconsult1(m): 2:52pm On May 10, 2024 |
Theanchor: 18" is 450mm, which is small for the required width. Minimum for the column base is 300mm, considering there will still be blinding of about 50mm 1 Like |
pconsult1(m): 2:55pm On May 10, 2024 |
Filling contd..
|
Theanchor: 4:06pm On May 10, 2024 |
pconsult1: Noted! But where the size of the blocks is 6inches, will the 450mm be considered adequate for the width? |
Kongaone: 5:14pm On May 10, 2024 |
Nice work. Long we saw this kind work for Nairaland. What's the estimated budget for this edifice pls? |
pconsult1(m): 9:00pm On May 10, 2024 |
Kongaone: Thanks for the compliments. 45m - carcass |
pconsult1(m): 9:01pm On May 10, 2024 |
Theanchor:Yes the width is okay for 6" |
Homextras: 8:41am On May 11, 2024 |
pconsult1:is this the budget for the whole project or just part? |
pconsult1(m): 9:59am On May 11, 2024 |
Homextras: Carcass |
pconsult1(m): 11:02am On May 11, 2024 |
Rammering and compacting
|
pconsult1(m): 5:29pm On May 11, 2024 |
We were able to cast the oversite concrete (German floor) despite a little delay by the rain.
|
pconsult1(m): 6:38am On May 12, 2024 |
The foundation has been duly completed yesterday.. From 1st of May to 11th of May. "We pleasingly design and build" Kindly us via call or whatsapp for your next building project anywhere in Nigeria too. Tel: 07011714010 |
pconsult1(m): 6:57am On May 13, 2024 |
Happy new week guys!! We will be starting off this week with ground floor block settings today and hoping to cast the lintel this weekend.
|
pconsult1(m): 10:44am On May 13, 2024 |
.
|
pconsult1(m): 4:16pm On May 13, 2024 |
Ground floor blockwork
|
pconsult1(m): 4:20pm On May 13, 2024 |
More pictures
|